A new two-story custom home on a wooded lot. Follow the build as the structure takes shape and work moves toward the next stages.
Progress update · November 18, 2026

The structure takes shape.
Recent site photographs show two-story timber framing and roof framing underway. The home is still under construction.
Where the build stands
Completed preparation & deliveries
Site cleanup, temporary fencing and a construction waste enclosure are recorded complete on November 5, followed by debris removal on November 10.
Structural material deliveries for both floors, including beams, stair components, floor decking, connectors and roof lumber, are recorded complete between November 10 and 16. These are delivery milestones; installation is still underway.
Next on the schedule
- November 18: Initial framing inspection and corrections, plumbing layout, and deliveries for exterior sheathing, cornices, siding and an exterior door.
- November 19–20: Cornice work, exterior door installation, plumbing top-out rough-in, siding and a framing/cornice walkthrough.
- November 23–December 1: Window flashing supplies, window delivery and installation, followed by scheduled HVAC rough-in and garage door work.
Schedule checked November 18, 2026. These activities remain planned/open and dates may change. Framing completion and a passed inspection have not yet been confirmed.